Which of the following are common characteristics of a critical path analysis?
A - HSC - SSCE Business Studies - Question 18 - 2024 - Paper 1
Question 18
Which of the following are common characteristics of a critical path analysis?
A. What tasks need to be done, how long they take, delivery timing
B. What tasks need... show full transcript
Worked Solution & Example Answer:Which of the following are common characteristics of a critical path analysis?
A - HSC - SSCE Business Studies - Question 18 - 2024 - Paper 1
Step 1
What tasks need to be done, how long they take, what order is necessary
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Option B is the correct answer. In critical path analysis, it is crucial to identify all the tasks involved in a project, their duration, and the sequence in which they must be completed. This helps in determining which tasks are critical to the project's timeline.