The diagram below shows a critical path analysis for a project - HSC - SSCE Business Studies - Question 14 - 2012 - Paper 1

Question icon

Question 14

The-diagram-below-shows-a-critical-path-analysis-for-a-project-HSC-SSCE Business Studies-Question 14-2012-Paper 1.png

The diagram below shows a critical path analysis for a project. The diagram includes: - Task A: 1 day - Task B: 3 days - Task C: 4 days - Task D: 1 day - Task E: 2 ... show full transcript

Worked Solution & Example Answer:The diagram below shows a critical path analysis for a project - HSC - SSCE Business Studies - Question 14 - 2012 - Paper 1

Step 1

Calculate Path Times

96%

114 rated

Answer

To determine the minimum duration for project completion, we will analyze the different paths in the critical path analysis:

  1. Path 1: Start → Task A (1 day) → Task B (3 days) → Task F (3 days) → Task G (10 days) → Finish
    Total: 1 + 3 + 3 + 10 = 17 days

  2. Path 2: Start → Task A (1 day) → Task C (4 days) → Task F (3 days) → Task G (10 days) → Finish
    Total: 1 + 4 + 3 + 10 = 18 days

  3. Path 3: Start → Task A (1 day) → Task D (1 day) → Task E (2 days) → Task I (4 days) → Finish
    Total: 1 + 1 + 2 + 4 = 8 days

  4. Path 4: Start → Task A (1 day) → Task D (1 day) → Task H (5 days) → Task G (10 days) → Finish
    Total: 1 + 1 + 5 + 10 = 17 days

After analyzing all paths, the longest path, which determines the critical path, is 17 days.

Step 2

Identify Minimum Completion Time

99%

104 rated

Answer

The minimum number of days needed to complete the project is the maximum total of all paths calculated. Therefore, the minimum number of days needed is 17 days.