The diagram below shows a critical path analysis for a project - HSC - SSCE Business Studies - Question 14 - 2012 - Paper 1
Question 14
The diagram below shows a critical path analysis for a project.
The diagram includes:
- Task A: 1 day
- Task B: 3 days
- Task C: 4 days
- Task D: 1 day
- Task E: 2 ... show full transcript
Worked Solution & Example Answer:The diagram below shows a critical path analysis for a project - HSC - SSCE Business Studies - Question 14 - 2012 - Paper 1
Step 1
Calculate Path Times
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To determine the minimum duration for project completion, we will analyze the different paths in the critical path analysis:
Path 1: Start → Task A (1 day) → Task B (3 days) → Task F (3 days) → Task G (10 days) → Finish
Total: 1 + 3 + 3 + 10 = 17 days
Path 2: Start → Task A (1 day) → Task C (4 days) → Task F (3 days) → Task G (10 days) → Finish
Total: 1 + 4 + 3 + 10 = 18 days
Path 3: Start → Task A (1 day) → Task D (1 day) → Task E (2 days) → Task I (4 days) → Finish
Total: 1 + 1 + 2 + 4 = 8 days
Path 4: Start → Task A (1 day) → Task D (1 day) → Task H (5 days) → Task G (10 days) → Finish
Total: 1 + 1 + 5 + 10 = 17 days
After analyzing all paths, the longest path, which determines the critical path, is 17 days.
Step 2
Identify Minimum Completion Time
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The minimum number of days needed to complete the project is the maximum total of all paths calculated. Therefore, the minimum number of days needed is 17 days.