What is the length of the critical path for this project?
(A) 9 days
(B) 14 days
(C) 18 days
(D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1
Question 14
What is the length of the critical path for this project?
(A) 9 days
(B) 14 days
(C) 18 days
(D) 27 days
Worked Solution & Example Answer:What is the length of the critical path for this project?
(A) 9 days
(B) 14 days
(C) 18 days
(D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1
Step 1
Calculate the critical path length
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To determine the length of the critical path, we need to analyze the project activities and their dependencies. The critical path is the longest duration path through a project, determining the shortest time to complete the project.
List all activities: Identify all activities involved in the project along with their durations and dependencies.
Create a network diagram: Visualize the activities and their interdependencies to see how they relate to each other.
Calculate paths: Measure the total time for each possible path through the network.
Identify the longest path: The critical path is the one with the maximum total duration. In this case, based on the provided options, the length of the critical path is 18 days, which corresponds to option (C).