If activity EC is delayed and takes 6 days, by how long will the project be delayed? (A) 0 days (B) 3 days (C) 6 days (D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1

Question icon

Question 15

If-activity-EC-is-delayed-and-takes-6-days,-by-how-long-will-the-project-be-delayed?--(A)-0-days-(B)-3-days-(C)-6-days-(D)-17-days-HSC-SSCE Business Studies-Question 15-2015-Paper 1.png

If activity EC is delayed and takes 6 days, by how long will the project be delayed? (A) 0 days (B) 3 days (C) 6 days (D) 17 days

Worked Solution & Example Answer:If activity EC is delayed and takes 6 days, by how long will the project be delayed? (A) 0 days (B) 3 days (C) 6 days (D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1

Step 1

Determine the impact of the delay

96%

114 rated

Answer

When an activity in a project is delayed, its duration directly influences the overall project timeline. In this case, activity EC is delayed by 6 days.

To assess the overall project delay, we need to consider the position of activity EC within the project schedule, particularly whether it is on the critical path or not.

Step 2

Critical path analysis

99%

104 rated

Answer

If activity EC is part of the critical path, the total project duration would be extended by 6 days due to the delay. Conversely, if it is not on the critical path, then the project may not be delayed.

Assuming that EC is indeed on the critical path, the project will be delayed by exactly 6 days.

Step 3

Select the correct answer

96%

101 rated

Answer

Given that the activity is delayed by 6 days, the correct answer is (C) 6 days.