Photo AI

The network diagram shows the time needed for each step in order to complete a project - HSC - SSCE Mathematics Standard - Question 3 - 2022 - Paper 1

Question icon

Question 3

The-network-diagram-shows-the-time-needed-for-each-step-in-order-to-complete-a-project-HSC-SSCE Mathematics Standard-Question 3-2022-Paper 1.png

The network diagram shows the time needed for each step in order to complete a project. What is the critical path to complete the project? A. ACI B. ADG C. BEH D. ... show full transcript

Worked Solution & Example Answer:The network diagram shows the time needed for each step in order to complete a project - HSC - SSCE Mathematics Standard - Question 3 - 2022 - Paper 1

Step 1

What is the critical path to complete the project?

96%

114 rated

Answer

To determine the critical path, we need to calculate the total time for each potential path in the network diagram.

Let's analyze the paths:

  • Path ACI: A (3) + C (16) + I (2) = 3 + 16 + 2 = 21
  • Path ADG: A (3) + D (16) + G (22) = 3 + 16 + 22 = 41
  • Path BEH: B (2) + E (9) + H (6) = 2 + 9 + 6 = 17
  • Path BEFG: B (2) + E (9) + F (19) + G (22) = 2 + 9 + 19 + 22 = 52

From the calculations:

  • The total time for ACI is 21.
  • The total time for ADG is 41.
  • The total time for BEH is 17.
  • The total time for BEFG is 52.

The critical path is the one with the longest duration, which in this case is ADG with a total time of 41. Therefore, the answer is B. ADG.

Join the SSCE students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;