Question 9
The time taken to paint a school varies inversely with the number of painters completing the task.
It takes 6 painters a total of 20 days to paint a school.
How ma... show full transcript
Worked Solution & Example Answer:The time taken to paint a school varies inversely with the number of painters completing the task - HSC - SSCE Mathematics Standard - Question 9 - 2024 - Paper 1
Step 1
Determine the relationship and calculate total painter-days
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The time taken to paint is inversely proportional to the number of painters. We can express this as:
T=Pk
where:
T is the time in days,
P is the number of painters,
k is a constant.
When 6 painters take 20 days, we find:
k=T×P=20×6=120 painter-days
Step 2
Calculate time for 15 painters
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Now we need to find how long it takes 15 painters, using the derived constant:
T=Pk=15120=8 days
Therefore, it would take 15 painters a total of 8 days to paint the school.