The time taken to paint a school varies inversely with the number of painters completing the task. It takes 6 painters a total of 20 days to paint a school. How ma... show full transcript

Worked Solution & Example Answer:The time taken to paint a school varies inversely with the number of painters completing the task - HSC - SSCE Mathematics Standard - Question 9 - 2024 - Paper 1

Step 1

Determine the relationship and calculate total painter-days

96%

114 rated

Answer

The time taken to paint is inversely proportional to the number of painters. We can express this as:

T=kPT = \frac{k}{P}

where:

  • TT is the time in days,
  • PP is the number of painters,
  • kk is a constant.

When 6 painters take 20 days, we find:

k=T×P=20×6=120 painter-daysk = T \times P = 20 \times 6 = 120 \text{ painter-days}

Step 2

Calculate time for 15 painters

99%

104 rated

Answer

Now we need to find how long it takes 15 painters, using the derived constant:

T=kP=12015=8 daysT = \frac{k}{P} = \frac{120}{15} = 8 \text{ days}

Therefore, it would take 15 painters a total of 8 days to paint the school.