Critical Path Analysis (CPA) is a method for analysing an activity network to determine the minimum project duration, identify critical activities, and calculate key timings. It also helps determine the minimum number of workers required to complete the project efficiently.
The critical path is the longest path through the network. It determines the minimum time required to complete the project. Activities on the critical path have zero float.
Question Consider the precedence table below:
Activity | Duration | Immediate Predecessors |
---|---|---|
A | 3 | - |
B | 2 | A |
C | 4 | A |
D | 5 | B, C |
E | 3 | C |
F | 6 | D, E |
Step 1: Draw the Activity Network
Construct the network with a single start node, a single end node, and all dependencies shown.
Step 2: Forward Pass
Step 3: Backward Pass
Step 4: Identify Critical Activities
Project Duration: 18 units.
Step 5: Calculate Lower Bound for Workers
At least 2 workers are required to complete the project in the shortest possible time.
Incorrect Timings in Forward/Backward Pass Forgetting to take the maximum for EET or minimum for LET leads to incorrect critical paths.
Confusion Between Float and Timings Misinterpreting float as the difference between EET and LET instead of LFT and EFT.
Missing Dependencies Failing to include all immediate predecessors or successors can cause errors in the network.
Incorrect Lower Bound Calculation Using project duration instead of total activity time or vice versa.
Overlooking Critical Activities Not correctly identifying zero float activities as critical.
Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!
70 flashcards
Flashcards on Critical Path Analysis
Revise key concepts with interactive flashcards.
Try Further Maths Decision Maths 1 Flashcards7 quizzes
Quizzes on Critical Path Analysis
Test your knowledge with fun and engaging quizzes.
Try Further Maths Decision Maths 1 Quizzes29 questions
Exam questions on Critical Path Analysis
Boost your confidence with real exam questions.
Try Further Maths Decision Maths 1 Questions27 exams created
Exam Builder on Critical Path Analysis
Create custom exams across topics for better practice!
Try Further Maths Decision Maths 1 exam builder50 papers
Past Papers on Critical Path Analysis
Practice past papers to reinforce exam experience.
Try Further Maths Decision Maths 1 Past PapersDiscover More Revision Notes Related to Critical Path Analysis to Deepen Your Understanding and Improve Your Mastery
96%
114 rated
Critical Path Analysis
Activity Networks & Precedence Tables
354+ studying
195KViewsJoin 500,000+ A-Level students using SimpleStudy...
Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!
Report Improved Results
Recommend to friends
Students Supported
Questions answered