Photo AI

Last Updated Sep 27, 2025

Gantt (Cascade) Charts Simplified Revision Notes

Revision notes with simplified explanations to understand Gantt (Cascade) Charts quickly and effectively.

user avatar
user avatar
user avatar
user avatar
user avatar

448+ students studying

11.1.4 Gantt (Cascade) Charts

Introduction

Gantt charts (also known as cascade charts) are a visual tool used to schedule and manage projects. They provide a timeline view of activities and highlight when tasks start, their durations, and how they relate to one another.

In A-Level Further Maths, Gantt charts are closely tied to Critical Path Analysis (CPA). We often calculate the total float of an activity and use this to schedule tasks efficiently on a Gantt chart, ensuring each activity requires only one worker at a time.

Total Float

The total float of an activity is the amount of time that an activity can be delayed without affecting the overall project completion time. It is calculated using:

Total Float (TF)=LEd\text{Total Float (TF)} = L - E - d

where:

  • LL: Latest Finish Time (LFT) of the activity,
  • EE: Earliest Start Time (EST) of the activity,
  • dd: Duration of the activity.

If the total float is zero, the activity lies on the critical path, meaning it must start and finish on time to avoid delaying the project.

Gantt (Cascade) Chart

A Gantt chart represents activities as horizontal bars along a timeline. It visually shows:

  • When an activity starts and finishes.
  • Dependencies between activities.
  • Float for non-critical activities (shown by extending bars).

Worked Examples

infoNote

Example 1: Calculate Total Float and Draw a Gantt Chart

Step 1: Given Information

Consider the following activities, their durations, and the earliest and latest times:

ActivityDuration (dd)Earliest Start (EE)Latest Finish (LL)
A406
B349
C279
D5010

Step 2: Calculate Total Float

Using TF=LEd\text{TF} = L - E - d:

  • Activity AA: TF=604=:success[2]TF = 6 - 0 - 4 = :success[2]
  • Activity BB: TF=943=:success[2]TF = 9 - 4 - 3 = :success[2]
  • Activity CC: TF=972=:highlight[0]TF = 9 - 7 - 2 = :highlight[0] (critical activity)
  • Activity DD: TF=1005=:success[5]TF = 10 - 0 - 5 = :success[5]

Step 3: Draw the Gantt Chart

  • Activity A: Starts at time 00, duration 44, and has 22 units of float.
  • Activity B: Starts at time 44, duration 33, and has 22 units of float.
  • Activity C: Starts at time 77, duration 22, and no float (critical path).
  • Activity D: Starts at time 00, duration 55, and has 55 units of float.

Visualizing the Gantt chart:

Time:       0   1   2   3   4   5   6   7   8   9   10
Activity A: ████----
Activity B:     ███----
Activity C:             ██
Activity D: █████----

Key:

  • : Task duration.
  • - : Float.
infoNote

Example 2: Construct a Gantt Chart for Dependencies

Step 1: Given Information

The project has the following dependencies:

ActivityDuration (dd)Depends onEarliest Start (EE)Latest Finish (LL)
A2-03
B3A26
C4A26
D5B, C612

Step 2: Calculate Total Float

  • Activity AA: TF=302=:success[1]TF = 3 - 0 - 2 = :success[1]
  • Activity BB: TF=623=:success[1]TF = 6 - 2 - 3 = :success[1]
  • Activity CC: TF=624=:highlight[0]TF = 6 - 2 - 4 = :highlight[0] (critical activity)
  • Activity DD: TF=1265=:success[1]TF = 12 - 6 - 5 = :success[1]

Step 3: Draw the Gantt Chart

Considering the dependencies:

  • AA starts at time 00, duration 22, and has 11 unit of float.
  • BB and CC depend on AA, so they cannot start before time 22.
  • DD depends on BB and CC, so it cannot start before time 66.

Visualizing the Gantt chart:

Time:       0   1   2   3   4   5   6   7   8   9   10  11  12
Activity A: ██-
Activity B:     ███-
Activity C:     ████
Activity D:             █████

Note Summary

infoNote

Common Mistakes

  1. Incorrect float calculation: Forgetting to subtract the duration (dd) in TF=LEdTF = L - E - d
  2. Misinterpreting dependencies: Starting an activity before all its predecessors are complete.
  3. Omitting float on the Gantt chart: Ensure that float is shown for non-critical activities.
  4. Overlapping activities requiring one worker: Assign only one worker per activity to avoid conflicts.
  5. Failing to identify the critical path: Recognize activities with zero float as critical.
infoNote

Key Formulas

  1. Total float:
TF=LEdTF = L - E - d
  1. Earliest Start Time (EST): The earliest time an activity can start, based on its predecessors.
  2. Latest Finish Time (LFT): The latest time an activity can finish without delaying the project.
  3. Gantt chart bars:
  • Bar length = duration.
  • Extend bar for float if present.
  1. Dependencies:
  • Activities must start only after their predecessors are completed.
Books

Only available for registered users.

Sign up now to view the full note, or log in if you already have an account!

500K+ Students Use These Powerful Tools to Master Gantt (Cascade) Charts

Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!

70 flashcards

Flashcards on Gantt (Cascade) Charts

Revise key concepts with interactive flashcards.

Try Further Maths Decision Maths 1 Flashcards

7 quizzes

Quizzes on Gantt (Cascade) Charts

Test your knowledge with fun and engaging quizzes.

Try Further Maths Decision Maths 1 Quizzes

29 questions

Exam questions on Gantt (Cascade) Charts

Boost your confidence with real exam questions.

Try Further Maths Decision Maths 1 Questions

27 exams created

Exam Builder on Gantt (Cascade) Charts

Create custom exams across topics for better practice!

Try Further Maths Decision Maths 1 exam builder

50 papers

Past Papers on Gantt (Cascade) Charts

Practice past papers to reinforce exam experience.

Try Further Maths Decision Maths 1 Past Papers

Other Revision Notes related to Gantt (Cascade) Charts you should explore

Discover More Revision Notes Related to Gantt (Cascade) Charts to Deepen Your Understanding and Improve Your Mastery

96%

114 rated

Critical Path Analysis

Activity Networks & Precedence Tables

user avatar
user avatar
user avatar
user avatar
user avatar

486+ studying

181KViews

96%

114 rated

Critical Path Analysis

Dummy Activities

user avatar
user avatar
user avatar
user avatar
user avatar

375+ studying

183KViews

96%

114 rated

Critical Path Analysis

Critical Path Analysis

user avatar
user avatar
user avatar
user avatar
user avatar

383+ studying

192KViews

96%

114 rated

Critical Path Analysis

Resource Histograms

user avatar
user avatar
user avatar
user avatar
user avatar

269+ studying

187KViews
Load more notes

Join 500,000+ A-Level students using SimpleStudy...

Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!

97% of Students

Report Improved Results

98% of Students

Recommend to friends

500,000+

Students Supported

50 Million+

Questions answered