Photo AI

Harrington Ltd has recently completed its annual sales forecast for the year ended 31/12/2023 - Leaving Cert Accounting - Question 9 - 2022

Question icon

Question 9

Harrington-Ltd-has-recently-completed-its-annual-sales-forecast-for-the-year-ended-31/12/2023-Leaving Cert Accounting-Question 9-2022.png

Harrington Ltd has recently completed its annual sales forecast for the year ended 31/12/2023. It expects to sell two products – Golden at €360 and Portland at €410... show full transcript

Worked Solution & Example Answer:Harrington Ltd has recently completed its annual sales forecast for the year ended 31/12/2023 - Leaving Cert Accounting - Question 9 - 2022

Step 1

Prepare a production budget (in units).

96%

114 rated

Answer

To prepare the production budget, we start with the expected sales and adjust for opening and closing stock:

  1. Expected Sales:

    • Golden: 15,200 units
    • Portland: 8,400 units
  2. Add Closing Stock:

    • Golden: 10% of 15,200 = 1,520 units
    • Portland: 10% of 8,400 = 840 units
  3. Less Opening Stock:

    • Golden: 900 units
    • Portland: 750 units
  4. Budgeted Production Calculation:

    • For Golden:

    Budgeted Production = Expected Sales + Closing Stock - Opening Stock
    = 15,200 + 1,520 - 900
    = 15,820 units

    • For Portland:
      Budgeted Production = Expected Sales + Closing Stock - Opening Stock
      = 8,400 + 840 - 750
      = 8,490 units

Thus, the production budget is:

  • Golden: 15,820 units
  • Portland: 8,490 units

Step 2

Prepare a raw materials purchases budget (in kg and €).

99%

104 rated

Answer

To prepare the raw materials purchases budget, we need to consider the requirements for production and adjust for stocks:

  1. Calculate Total Requirement for Production:

    • Material A for Golden: 15,820 units * 6 Kgs/unit = 94,920 Kgs

    • Material A for Portland: 8,490 units * 8 Kgs/unit = 67,920 Kgs

    • Total Material A Required = 94,920 + 67,920 = 162,840 Kgs

    • Material B for Golden: 15,820 units * 9 Kgs/unit = 142,380 Kgs

    • Material B for Portland: 8,490 units * 12 Kgs/unit = 101,880 Kgs

    • Total Material B Required = 142,380 + 101,880 = 244,260 Kgs

  2. Add Closing Stock:

    • Material A (10% of required): 16,284 Kgs
    • Material B (10% of required): 24,426 Kgs
  3. Less Opening Stock:

    • Material A: 9,400 Kgs
    • Material B: 6,800 Kgs
  4. Purchases Calculation:

    • Purchases for Material A = 162,840 + 16,284 - 9,400 = 169,724 Kgs
    • Purchases for Material B = 244,260 + 24,426 - 6,800 = 262,886 Kgs

Finally, convert the quantity into monetary value using the expected prices (Material A at €5.50 and Material B at €7.00):

  • Cost of Material A = 169,724 Kgs * €5.50 = €933,462
  • Cost of Material B = 262,886 Kgs * €7.00 = €1,836,202

Total Purchase Cost:

  • Material A: €933,462
  • Material B: €1,836,202

Thus, the raw materials purchases budget shows Material A costing €933,462 and Material B costing €1,836,202.

Step 3

Prepare a production cost/manufacturing budget.

96%

101 rated

Answer

To construct the production cost/manufacturing budget, we account for direct materials, direct labor, variable overheads, and fixed overheads:

  1. Direct Materials Costs Calculation:

    • Opening Stock:
      • Material A: 9,400 Kgs * €5.00 = €47,000
      • Material B: 6,800 Kgs * €6.50 = €44,200
    • Raw Materials Purchases:
      • Material A: €933,462 (from previous step)
      • Material B: €1,836,202 (from previous step)
    • Total Raw Material Costs:
      • Material A total cost = €47,000 + €933,462 - (closing stock adjustment)
      • Material B total cost = €44,200 + €1,836,202 - (closing stock adjustment)
  2. Direct Labor Costs Calculation:

    • For Golden: 15,820 units * 6 hours/unit * €18 = €1,705,320
    • For Portland: 8,490 units * 9 hours/unit * €18 = €1,366,020
  3. Variable Overheads Calculation:

    • For Golden: 15,820 units * 6 hours/unit * €12 = €1,140,080
    • For Portland: 8,490 units * 9 hours/unit * €12 = €915,720
  4. Fixed Overheads:

    • Fixed Costs = €579,550
  5. Total Production Cost:

    • Sum of all costs calculated above to obtain overall cost of manufacture.

Step 4

Prepare a budgeted trading account.

98%

120 rated

Answer

To formulate the budgeted trading account for the year ended 31/12/2023:

  1. Calculate Total Sales:

    • Sales from Golden: 15,200 units * €360 = €5,472,000
    • Sales from Portland: 8,400 units * €410 = €3,444,000
    • Total Sales = €5,472,000 + €3,444,000 = €8,916,000
  2. Less Cost of Sales:

    • Calculate cost of goods sold = opening stock + production costs - closing stock (refer to production costs from previous steps).

    • Opening Stock for finished goods:

      • Golden: 900 units * €210 = €189,000
      • Portland: 750 units * €290 = €217,500
    • Total Opening Stock = €189,000 + €217,500 = €406,500

    • Calculate the correct Cost of Goods Sold and subtract from Total Sales.

    • Less Closing Stock Value (calculate based on final valuations).

  3. Gross Profit Calculation:

    • Gross Profit = Total Sales - Cost of Sales

Provide detailed figures for each of these sections to tally the final gross profit.

Step 5

Outline why budget control is necessary in an organisation.

97%

117 rated

Answer

Budget control is critical for several reasons:

  1. Performance Plans: Budgets serve as performance benchmarks, guiding organizations in planning and executing financial goals.
  2. Resource Allocation: Ensure resources, including finances and manpower, are correctly allocated to maximize efficiency.
  3. Cost Management: Help in controlling operational costs by setting financial limits.
  4. Responsibility: Designate areas of responsibility to ensure that each department meets its targets and contributes to overall performance.
  5. Variance Analysis: Identify any variances in expected vs. actual figures, allowing an organization to make necessary adjustments in operations or finances.

Step 6

Explain what is meant by a favourable variance and give an example of how it might arise in the direct costs of a manufacturing firm.

97%

121 rated

Answer

A favourable variance occurs when the actual costs are less than the budgeted costs, indicating better-than-anticipated performance.

For example, in manufacturing:

  • If the budgeted labor cost for a project was €50,000 but the actual cost ended up being €45,000, this results in a favourable variance of €5,000.
  • This could arise from efficiencies in labor usage or successfully negotiating lower wage rates than originally anticipated.

Join the Leaving Cert students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;