The eaves of a timber flat roof for a bathroom is constructed as shown in the sketch. The roof is covered with layers of bituminous felt on plywood decking on 200 mm... show full transcript

Worked Solution & Example Answer:The eaves of a timber flat roof for a bathroom is constructed as shown in the sketch - Leaving Cert Construction Studies - Question 1 - 2013

Step 1

To a scale of 1:5, draw a vertical section through the eaves of the flat roof and through the external wall.

96%

114 rated

Answer

  1. Start by drawing a vertical line to represent the section width. This line should be proportionate to the scale selected, specifically 1:5.

  2. Illustrate the roof structure beginning with the outermost layer, which includes three layers of bituminous felt, followed by plywood decking measuring 18-25 mm.

  3. Below the decking, depict the counter battens and the roof joists which are 200 mm × 50 mm placed at 450 mm centres.

  4. Indicate the insulation layer, specifying that it’s 150 mm in thickness to comply with current Building Regulations.

  5. Include the plasterboard ceiling below and finish the section with the external wall, detailing the 350 mm concrete block wall.

  6. Ensure to include dimensions where required:

    • Distance from the wallplate to the edge of the joist
    • Total height of the wall
    • Thickness of the insulation
    • Length of the fascia so that it shows variations clearly. Each measurement should be clearly marked on the drawing to match the 1.5 m representation of the roof joist.

Step 2

On your drawing, show how rainwater is removed from the flat roof.

99%

104 rated

Answer

  1. Illustrate a drip edge formed from a material of 50 mm × 25 mm attached to the fascia. This serves as a channel for rainwater.

  2. Show the direction of water flow beginning from the roof surface, moving towards the eaves gutter, which should be appropriately sized to capture the water.

  3. Depict how the eaves gutter is fitted directly under the drip edge and is sealed to ensure no leakage occurs.

  4. Add a downpipe connected to the eaves gutter that directs the collected water downwards and away from the building's foundation.

  5. Make sure to clearly label all parts of the drainage system including the gutter, downpipe, and drip edge, along with arrows to indicate the direction of water flow for clarity.

Join the Leaving Cert students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;