1. Name the type of building that is illustrated by FIGURE A - NSC Civil Technology Civil Services - Question 2 - 2024 - Paper 1
Question 2
1. Name the type of building that is illustrated by FIGURE A.
The building illustrated in Figure A is a multi-storey building, specifically a three-storey buildi... show full transcript
Worked Solution & Example Answer:1. Name the type of building that is illustrated by FIGURE A - NSC Civil Technology Civil Services - Question 2 - 2024 - Paper 1
Step 1
Name the type of building that is illustrated by FIGURE A.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The building illustrated in Figure A is a multi-storey building, specifically a three-storey building.
Step 2
Deduce from the building plan the elevation on which the sink is located.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The sink is located in the North elevation as indicated in the building plan.
Step 3
Identify number 1.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Number 1 refers to the ridge capping, which is a roof covering feature.
Step 4
Why are balusters installed at number 2?
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Balusters are installed at number 2 to prevent people from falling off the edge of the construction.
Step 5
What type of material was specified for number 3?
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The material specified for number 3 is laminated safety glass.
Step 6
Recommend ONE suitable material for number 4.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
A suitable material for number 4 would be timber or fibre cement.
Step 7
Who is the owner of the proposed dwelling?
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The owner of the proposed dwelling is Mr. P Xhosa.
Step 8
Identify the number that indicates the downpipe.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The number indicating the downpipe is 5.
Step 9
Name ONE other sanitary fixture, besides a washbasin, that can be installed in the bathroom.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
A shower can be installed in the bathroom as another sanitary fixture.
Step 10
Identify number 7.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Number 7 refers to the distribution board (DB).
Step 11
Describe the purpose of number 8.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The purpose of number 8 is to provide access to the garage with a vehicle.
Step 12
How many fluorescent tubes are indicated in the building?
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
There is 1 fluorescent tube indicated in the building.
Step 13
Name the street in which the new building will be erected.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The new building will be erected on Protea Street.
Step 14
What type of finish was specified for the walls?
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The specified finish for the walls is stone cladding.
Step 15
Deduce from the building plan why it was revised.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The building plan was revised because drawings of the balustrades were not included.
Step 16
What must be installed to gain access to the first and second floor?
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Stairs must be installed to gain access to the first and second floors.
Step 17
Deduce from the building plan who must sign off the building plan.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The individuals who must sign off the building plan are the architect and client.
Step 18
What are the prescribed dimensions for the balusters?
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The dimensions prescribed for the balusters are 40 mm x 40 mm x 1 200 mm.
Step 19
Calculate the total height of the building from the finished floor level up to the top of the roof. Give your answer in m.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Total height = 2 600 + 2 600 + 170 + 1 800 = 9 940 mm = 9.94 m.
Step 20
Calculate the area of the external wall of the second floor from the top of the floor up to roof height in the west elevation in FIGURE A. Show all calculations. Give your answer in m².