Start the drawing from corner A, as indicated in the bottom left-hand corner of the sheet - NSC Civil Technology Civil Services - Question 1 - 2017 - Paper 1

Question icon

Question 1

Start-the-drawing-from-corner-A,-as-indicated-in-the-bottom-left-hand-corner-of-the-sheet-NSC Civil Technology Civil Services-Question 1-2017-Paper 1.png

Start the drawing from corner A, as indicated in the bottom left-hand corner of the sheet. 1. Draw the wall and both the bottom and side. 2. The overall height of t... show full transcript

Worked Solution & Example Answer:Start the drawing from corner A, as indicated in the bottom left-hand corner of the sheet - NSC Civil Technology Civil Services - Question 1 - 2017 - Paper 1

Step 1

1. Draw the wall and both the bottom and side.

96%

114 rated

Answer

To begin, ensure the wall is accurately represented in the drawing. The wall should be both vertical and level, with appropriate proportions according to the scale being used.

Step 2

2. The overall height of the building on the visible side of the house.

99%

104 rated

Answer

Measure the total height from the ground to the apex of the roof on the visible side. This should be reflected in the drawing visibly to maintain scale.

Step 3

3. Waste from the original roof - indicate room for the position of its indicated.

96%

101 rated

Answer

Indicate where waste from the original roof will go. This can be shown in the drawing with directional arrows that lead to a designated area.

Step 4

4. Show a valid cost in the bottom left hand corner and a symbol.

98%

120 rated

Answer

Include a symbol in the bottom left corner of the drawing that represents the estimated cost. This should be clear and aligned with industry standards for clarity.

Step 5

5. The screed symbol.

97%

117 rated

Answer

Add the screed symbol to the drawing to indicate the level surface required for the flooring. This symbol should be noted for practical application during construction.

Step 6

6. Concrete floor drawn correctly.

97%

121 rated

Answer

The concrete floor should be represented in the drawing, showing thickness and layers if necessary. Ensure all dimensions are clear and correct.

Step 7

7. Backfilling drawn correctly.

96%

114 rated

Answer

Indicate backfilling in the drawing with appropriate symbols or shading to represent the fill material used to support the structure. This should align with construction standards.

Step 8

8. DPC drawn in correct place.

99%

104 rated

Answer

Ensure the damp proof course (DPC) is clearly illustrated in the drawing, positioned correctly within the wall structure to prevent moisture ingress.