3.1 FIGURE 3.1 below is a drawing of a temporary excavation exposing the existing foundations - NSC Civil Technology Civil Services - Question 3 - 2021 - Paper 1

Question icon

Question 3

3.1--FIGURE-3.1-below-is-a-drawing-of-a-temporary-excavation-exposing-the-existing-foundations-NSC Civil Technology Civil Services-Question 3-2021-Paper 1.png

3.1 FIGURE 3.1 below is a drawing of a temporary excavation exposing the existing foundations. Study the drawing and answer the questions that follow. What does A ... show full transcript

Worked Solution & Example Answer:3.1 FIGURE 3.1 below is a drawing of a temporary excavation exposing the existing foundations - NSC Civil Technology Civil Services - Question 3 - 2021 - Paper 1

Step 1

What does A indicate on this drawing?

96%

114 rated

Answer

A indicates the ground level before excavation, also known as NGL (Natural Ground Level).

Step 2

Identify B.

99%

104 rated

Answer

B refers to the concrete slab or floor slab that is part of the existing foundations.

Step 3

Excavations always cause some ground movement. Name any TWO factors that can cause ground movement.

96%

101 rated

Answer

Two factors that can cause ground movement include:

  1. Blasting
  2. Piling

Step 4

Deduce the slope of the excavation from the drawing.

98%

120 rated

Answer

The slope of the excavation can be deduced as 1:2 or 1:1 based on the drawing.

Step 5

Name the TWO acceptable colours for the warning signals that should be visible around excavations.

97%

117 rated

Answer

The two acceptable colours for warning signals are:

  1. Red
  2. Orange

Step 6

Name TWO items that should NOT be placed near the edge of an excavation.

97%

121 rated

Answer

Two items that should not be placed near the edge of an excavation include:

  1. Any type of load
  2. Heavy machinery or vehicles

Step 7

Describe briefly the process of soil compaction.

96%

114 rated

Answer

Soil compaction is the process of increasing the density of soil by pressing the soil particles closer together. This can also be achieved by reducing the volume of air trapped between the particles using hand compaction methods or a rammer.

Step 8

Identify the construction in FIGURE 3.6.

99%

104 rated

Answer

The construction in FIGURE 3.6 is a shoring apparatus used to support the sides of the excavation.

Step 9

Explain the purpose of the sides of the construction.

96%

101 rated

Answer

The sides of the construction serve to support the excavation and ensure that the sides do not cave in, thereby protecting workers.

Step 10

STATE the formula that you will use to calculate the volume of a cubical water tank.

98%

120 rated

Answer

The formula to calculate the volume of a cubical water tank is:

Volume=Side3Volume = \text{Side}^3

Step 11

Give the amount of water in litres that you would need to fill a tank of 1 m³.

97%

117 rated

Answer

To fill a tank of 1 m³, you would need 1000 litres of water since 1 m³ is equivalent to 1000 litres.