1.1 Choose a description from COLUMN B that matches an item in COLUMN A - NSC Civil Technology Civil Services - Question 1 - 2019 - Paper 1

Question icon

Question 1

1.1-Choose-a-description-from-COLUMN-B-that-matches-an-item-in-COLUMN-A-NSC Civil Technology Civil Services-Question 1-2019-Paper 1.png

1.1 Choose a description from COLUMN B that matches an item in COLUMN A. Write only the letter (A–K) next to the question numbers (1.1.1 to 1.1.8) in the ANSWER BOO... show full transcript

Worked Solution & Example Answer:1.1 Choose a description from COLUMN B that matches an item in COLUMN A - NSC Civil Technology Civil Services - Question 1 - 2019 - Paper 1

Step 1

1.1.1 PVA paint

96%

114 rated

Answer

B

Step 2

1.1.2 Guard rail

99%

104 rated

Answer

I

Step 3

1.1.3 Powder coating

96%

101 rated

Answer

A

Step 4

1.1.4 Builder's hoist

98%

120 rated

Answer

D

Step 5

1.1.5 Ladder

97%

117 rated

Answer

G

Step 6

1.1.6 Diagonal brace

97%

121 rated

Answer

F

Step 7

1.1.7 Galvanising

96%

114 rated

Answer

J

Step 8

1.1.8 Chute

99%

104 rated

Answer

E

Step 9

1.2 Explain TWO advantages of electroplating.

96%

101 rated

Answer

Electroplating offers several advantages. Firstly, it protects metals against corrosion, extending their lifespan and maintaining their appearance. Secondly, it improves the engineering and mechanical properties of metal, which can enhance the performance of components in various applications.

Step 10

1.3 Name the process when freshly cast concrete is kept moist for a specific period of time.

98%

120 rated

Answer

Curing

Step 11

1.4 Explain the purpose of keeping freshly cast concrete moist for a certain period of time after the concrete has been cast.

97%

117 rated

Answer

Keeping freshly cast concrete moist serves multiple purposes. It prevents rapid drying, which can lead to cracking and ensures that the concrete achieves its designed strength by allowing for proper hydration of the cement.

Step 12

1.5 You are transporting material on a construction site from one place to another. Describe TWO safety precautions that you will adhere to while transporting the material.

97%

121 rated

Answer

When transporting material, it is essential to secure it firmly to prevent shifting or falling. Additionally, maintaining a safe distance from the edges of platforms and ensuring that the load does not exceed the carrying capacity of the transport method are crucial safety precautions.

Step 13

1.6 Describe ONE safety factor that must be considered when using scaffold planks to erect a scaffold platform.

96%

114 rated

Answer

Scaffold planks should be made of solid wood that meets specified dimensions to ensure they can support the load and should be inspected regularly for defects to prevent failure during use.

Step 14

1.7.1 Identify the tool above.

99%

104 rated

Answer

The tool is a dumpy level.

Step 15

1.7.2 Predict ONE consequence if the instrument is NOT set level.

96%

101 rated

Answer

If the instrument is not set level, it will yield inaccurate readings, leading to improper placements or adjustments on a construction site.

Step 16

1.8.1 Identify the joining fixture above.

98%

120 rated

Answer

The joining fixture is a dowel joint.

Step 17

1.8.2 Name the fixing agent that should be used with this joining fixture.

97%

117 rated

Answer

A suitable fixing agent would be wood glue.

Step 18

1.8.3 Explain ONE use of this joining fixture.

97%

121 rated

Answer

This joining fixture is used to strengthen the connection between two wooden pieces, ensuring structural stability in furniture or framework.