3.1 Give ONE word/term for each of the following statements by choosing a word/term from the list - NSC Civil Technology Civil Services - Question 3 - 2020 - Paper 1
Question 3
3.1 Give ONE word/term for each of the following statements by choosing a word/term from the list. Write only the word/term next to the question numbers (3.1.1 to 3.... show full transcript
Worked Solution & Example Answer:3.1 Give ONE word/term for each of the following statements by choosing a word/term from the list - NSC Civil Technology Civil Services - Question 3 - 2020 - Paper 1
Step 1
3.1.1 The sides of the excavations are firm enough to support the soil.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Hard ground.
Step 2
3.1.2 The sides of the excavations may cave in and must be supported by poling boards.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Moderately firm ground.
Step 3
3.1.3 The sides of the excavations must be supported by walling boards and strata if the soil has loose patches.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Loose and waterlogged ground.
Step 4
3.1.4 Solid timbering or shutter board panels must be placed very close together so that muddy soil does not filter through the openings.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
OHS.
Step 5
3.1.5 Orange warning signals must be visible at all times at excavations.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
PPE.
Step 6
3.2 Name TWO methods of backfilling trenches.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Compaction/Fill and compact. 2. Jetting/Flowable fill.
Step 7
3.3.1 Identify the type of bond used to build the wall.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
English bond.
Step 8
3.3.2 Name the brick indicated by A.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Queen closer.
Step 9
3.3.3 Give the width of brick A in mm.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
55 mm.
Step 10
3.4 State any TWO safety and hygiene measures that they must adhere to in order to prevent infections.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Wear safety goggles. 2. Wear gloves.
Step 11
3.5.1 The Occupational Health and Safety Act, 1993 (Act 85 of 1993) (protects/prohibits) workers who enter confined spaces, such as manholes.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Protects.
Step 12
3.5.2 Only (competent/educated) persons are allowed to work in a manhole.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Competent.
Step 13
3.7.1 Volume of the tank in m³.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The volume of a cylinder is given by the formula: V = rac{22}{7} r^2 h, where r is the radius (0.9 m) and h is the height (2.8 m) yielding a volume of 7.13 m³.
Step 14
3.7.2 Volume of water in the tank in litres.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To convert to litres, multiply the volume in cubic meters by 1,000. Thus,\ 7.13\ m³ \times 1,000 = 7,130\ litres.