Various options are provided as possible answers to the following questions - NSC Civil Technology Civil Services - Question 1 - 2023 - Paper 1

Question icon

Question 1

Various-options-are-provided-as-possible-answers-to-the-following-questions-NSC Civil Technology Civil Services-Question 1-2023-Paper 1.png

Various options are provided as possible answers to the following questions. Choose the answer and write only the letter (A–D) next to the question numbers (1.1.1 to... show full transcript

Worked Solution & Example Answer:Various options are provided as possible answers to the following questions - NSC Civil Technology Civil Services - Question 1 - 2023 - Paper 1

Step 1

1.1.1 Electroplating is the process of …

96%

114 rated

Answer

Electroplating is the process of coating a metal with another metal using electrolysis. Hence, the correct answer is B.

Step 2

1.1.2 The process of keeping freshly cast concrete damp will …

99%

104 rated

Answer

Keeping freshly cast concrete damp will make it more watertight. Therefore, the correct answer is B.

Step 3

1.1.3 Why would you coat a metal with a layer of paint?

96%

101 rated

Answer

The primary purposes of coating a metal with paint are to prevent corrosion and to resist extreme temperatures. Thus, the correct answer is D, which includes both A and B.

Step 4

1.1.4 The minimum size of a wooden scaffold plank:

98%

120 rated

Answer

The minimum size of a wooden scaffold plank is 228 mm wide x 38 mm thick. Therefore, the correct answer is D.

Step 5

1.1.5 When using a scaffold, it must be inspected to ensure that …

97%

117 rated

Answer

When using a scaffold, it should be ensured that the scaffold is free from any defects. The appropriate answer is D, which includes all mentioned options.

Step 6

1.1.6 … of scaffolds should be secured vertically.

97%

121 rated

Answer

To ensure safety, standards are essential for securing scaffolds vertically. Hence, the correct answer is C.

Step 7

1.1.7 The guard rail on a scaffold will ensure that …

96%

114 rated

Answer

The guard rail on a scaffold ensures that a worker does not fall from the scaffold. Hence, the correct answer is A.

Step 8

1.1.8 Toe boards must be at least 150 mm high from the level of the …

99%

104 rated

Answer

Toe boards must be at least 150 mm high from the scaffold platform. Therefore, the answer is A.

Step 9

1.1.9 The employer must ensure that the rungs of wooden ladders are …

96%

101 rated

Answer

The employer must ensure that the rungs of wooden ladders are free from grease. Thus, the correct answer is B.

Step 10

1.1.10 The material safety data sheet for hazardous chemicals must have the following information:

98%

120 rated

Answer

The material safety data sheet should list the quantity in the container. Therefore, the correct answer is A.

Step 11

1.1.11 Stairways must be installed at a minimum of … degrees from the horizontal.

97%

117 rated

Answer

Stairways must be installed at a minimum of 30 degrees from the horizontal. So, the answer is B.

Step 12

1.1.12 The purpose of the builder's hoist is to transport …

97%

121 rated

Answer

The purpose of the builder's hoist is to transport workers and materials. Therefore, the answer is A.