Photo AI

3.1 FIGURE 3.1 below is a drawing of a temporary excavation exposing the existing foundations - NSC Civil Technology Civil Services - Question 3 - 2021 - Paper 1

Question icon

Question 3

3.1-FIGURE-3.1-below-is-a-drawing-of-a-temporary-excavation-exposing-the-existing-foundations-NSC Civil Technology Civil Services-Question 3-2021-Paper 1.png

3.1 FIGURE 3.1 below is a drawing of a temporary excavation exposing the existing foundations. Study the drawing and answer the questions that follow. 3.1.1 What do... show full transcript

Worked Solution & Example Answer:3.1 FIGURE 3.1 below is a drawing of a temporary excavation exposing the existing foundations - NSC Civil Technology Civil Services - Question 3 - 2021 - Paper 1

Step 1

What does A indicate on this drawing?

96%

114 rated

Answer

A indicates the ground level before excavation (NGL).

Step 2

Identify B.

99%

104 rated

Answer

B is identified as the floor slab.

Step 3

Excavations always cause some ground movement. Name any TWO factors that can cause ground movement.

96%

101 rated

Answer

Two factors that can cause ground movement include:

  • Blasting
  • Compaction

Step 4

Deduce the slope of the excavation from the drawing.

98%

120 rated

Answer

The slope of the excavation can be deduced as 1:2 or 1:2.

Step 5

Name the TWO acceptable colours for the warning signals that should be visible around excavations.

97%

117 rated

Answer

The two acceptable colours for warning signals are:

  • Red
  • Orange

Step 6

Name TWO items that should NOT be placed near the edge of an excavation.

97%

121 rated

Answer

Two items that should NOT be placed near the edge of an excavation are:

  • Any type of load
  • Heavy machinery/vehicles

Step 7

Describe briefly the process of soil compaction.

96%

114 rated

Answer

The process of soil compaction involves increasing the density of soil by pressing the soil particles closer together, or reducing the volume of air trapped between the particles using hand compaction methods or a rammer.

Step 8

Name ONE type of soil that will be suitable for the use of jetting as a compaction method.

99%

104 rated

Answer

Sandy soil is suitable for the use of jetting as a compaction method.

Step 9

Identify the construction in FIGURE 3.6.

96%

101 rated

Answer

The construction in FIGURE 3.6 is identified as shoring.

Step 10

Explain the purpose of the sides of the construction.

98%

120 rated

Answer

The purpose of the sides of the construction is to support the sides of the excavation and to ensure that the sides do not cave in.

Step 11

Study the drawing and calculate the volume of the tank in m³.

97%

117 rated

Answer

The volume of the cylindrical water tank can be calculated using the formula:

V=extAreaofbaseimesextheightV = ext{Area of base} imes ext{height}

where ext{Area of base} = rac{22}{7} imes r^2

For given dimensions:

  • Diameter = 1,600 mm → Radius = 800 mm → r = 0.8 m
  • Height = 3,100 mm → Height = 3.1 m

Calculating gives: V=(3.14)imes(0.8)2imes3.1=6.23extm3V = (3.14) imes (0.8)^2 imes 3.1 = 6.23 ext{ m}^3

Step 12

State the formula that you will use to calculate the volume of a cubical water tank.

97%

121 rated

Answer

The formula to calculate the volume of a cubical water tank is:

V=extAreaofbaseimesextheight=S3V = ext{Area of base} imes ext{height} = S^3

where S is the length of a side.

Step 13

Give the amount of water in litres that you would need to fill a tank of 1 m³.

96%

114 rated

Answer

To fill a tank of 1 m³, you would need 1,000 litres of water.

Join the NSC students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;