Question 5
5.1 FIGURE 5.1 below shows a pre-fabricated surface channel A and concrete shoe B.
5.1.1 Explain why reinforced concrete is preferred in the manufacturing of A.
5.... show full transcript
Worked Solution & Example Answer:5.1 FIGURE 5.1 below shows a pre-fabricated surface channel A and concrete shoe B - NSC Civil Technology Civil Services - Question 5 - 2022 - Paper 1
Step 1
5.1.1 Explain why reinforced concrete is preferred in the manufacturing of A.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Reinforced concrete is favored in the manufacturing of pre-fabricated surface channel A for several reasons:
Strength: Reinforced concrete is stronger than mass concrete, allowing it to bear heavier loads and resist wear over time.
Durability: It withstands significant forces from water flow, making it ideal for channels that often deal with heavy rainfall or liquid transport.
Hydraulic Efficiency: Reinforced concrete is designed to handle large volumes of water flow efficiently, preventing overflow and reducing the risk of structural damage.
Step 2
5.1.2 Describe the logic for having a fall/slope when positioning B.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The concrete shoe B must be positioned with a fall or slope to ensure:
Water Drainage: It facilitates the effective drainage of water away from the building, preventing water accumulation that could lead to structural damage.
Preventing Water Damage: A correct slope minimizes the risk of water pooling, which can cause erosion or deterioration of the concrete over time.
Step 3
5.2 Use this answer sheet and complete the fascia board, gutter and downpipe installation.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
In constructing the roof's fascia board, gutter, and downpipe, the following elements are essential:
Fascia Board: Begin by sketching the fascia board, ensuring it's connected securely to the roof structure.
Square Gutter: Draw the square gutter, integrating it with clip supports and ensuring correct alignment with the fascia board's edge.
Gutter Clip: Indicate the gutter clips that secure the gutter in place.
Offset: Create an offset at the point where the gutter transitions to the downpipe for proper angle and flow.
Downpipe: Position the downpipe with a smooth transition from the gutter, ensuring it directs water away from the building's foundation.
Holder Bats: Include holder bats that support the downpipe placement.
Rainwater Shoe: Finally, show the rainwater shoe connection at the base of the downpipe to guide water efficiently into drainage.
Step 4
5.3 Use the drawing and the information to draw the development of pipe A.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To develop pipe A, follow these steps:
Dividing the Circle: Divide the circle of the auxiliary view into 12 equal parts to determine measurement points for development.
Projection Lines: From each division, project vertical lines downward to establish the length of each section in the development.
Drawing the Development: Considering the pipe's diameter and curved nature, construct the development layout resulting in a flat pattern that maintains accurate proportions for each segment.
3 mm Seam: Ensure to include the 3 mm seam on both sides of the development, as this is essential for proper assembly.
Final Touches: Clearly label all lines, including construction lines, to enhance understanding and facilitate accurate assembly.