5.1 Classify the type of finish that can be obtained by using the following: 5.1.1 A Tyrolene machine 5.1.2 Hessian cloth or cement bag 5.2 State TWO purposes of screed - NSC Civil Technology Construction - Question 5 - 2020 - Paper 1

Question icon

Question 5

5.1-Classify-the-type-of-finish-that-can-be-obtained-by-using-the-following:-5.1.1-A-Tyrolene-machine-5.1.2-Hessian-cloth-or-cement-bag--5.2-State-TWO-purposes-of-screed-NSC Civil Technology Construction-Question 5-2020-Paper 1.png

5.1 Classify the type of finish that can be obtained by using the following: 5.1.1 A Tyrolene machine 5.1.2 Hessian cloth or cement bag 5.2 State TWO purposes of sc... show full transcript

Worked Solution & Example Answer:5.1 Classify the type of finish that can be obtained by using the following: 5.1.1 A Tyrolene machine 5.1.2 Hessian cloth or cement bag 5.2 State TWO purposes of screed - NSC Civil Technology Construction - Question 5 - 2020 - Paper 1

Step 1

5.1 Classify the type of finish that can be obtained by using the following: 5.1.1 A Tyrolene machine

96%

114 rated

Answer

The Tyrolene machine is used to achieve a splatter finish, commonly referred to as a splatter dash finish or roughcast finish.

Step 2

5.1.2 Hessian cloth or cement bag

99%

104 rated

Answer

Using hessian cloth or a cement bag results in a bagging finish, which provides a textured appearance to the surface.

Step 3

5.2 State TWO purposes of screed.

96%

101 rated

Answer

  1. To provide a smooth, level surface that can support various floor coverings.
  2. To enhance the structural depth and strength of the base slab.

Step 4

5.3 Explain ONE method of preparing a smooth concrete floor to receive the screed.

98%

120 rated

Answer

One effective method is to chip the surface with a sharp tool to remove the hard, surface skin and expose the fresh concrete underneath. Wetting the surface afterward can also improve adherence.

Step 5

5.4 Identify the material that can be added to plaster to increase its workability and plasticity.

97%

117 rated

Answer

Builders' lime can be added to plaster to enhance its workability and plasticity.

Step 6

5.5 Differentiate between a rough arch and a gauged arch in terms of the respective shapes of the mortar joints.

97%

121 rated

Answer

In a rough arch, the mortar joint will typically be wedge-shaped or triangular, while in a gauged arch, the mortar joint will be more uniform and rectangular in shape.

Step 7

5.6 Use ANSWER SHEET 5.6 and draw a neat sketch showing the alternate plan courses of a one-and-a-half brick pier built in stretcher bond.

96%

114 rated

Answer

The sketch should demonstrate alternating courses in a stretcher bond pattern, focusing on ensuring that joints between bricks are staggered for added stability.

Step 8

5.7 Use ANSWER SHEET 5.7 and draw to scale 1:10 a horizontal section through a wooden door frame built into a 220 mm wall.

99%

104 rated

Answer

The drawing must include details such as:

  • A brick wall measuring 220 mm
  • A door frame measuring 110 mm x 70 mm
  • A DPC attached to the door frame
  • Quarter rounds and labeled components. Ensure to use appropriate scaling and labels for clarity.

Join the NSC students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;