Photo AI

REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE FLOORS AND QUANTITIES (SPECIFIC) 6.1 Various options are given as possible answers to the following questions - NSC Civil Technology Construction - Question 6 - 2020 - Paper 1

Question icon

Question 6

REINFORCEMENT-IN-CONCRETE,-FOUNDATIONS,-CONCRETE-FLOORS-AND-QUANTITIES-(SPECIFIC)--6.1-Various-options-are-given-as-possible-answers-to-the-following-questions-NSC Civil Technology Construction-Question 6-2020-Paper 1.png

REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE FLOORS AND QUANTITIES (SPECIFIC) 6.1 Various options are given as possible answers to the following questions. Choo... show full transcript

Worked Solution & Example Answer:REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE FLOORS AND QUANTITIES (SPECIFIC) 6.1 Various options are given as possible answers to the following questions - NSC Civil Technology Construction - Question 6 - 2020 - Paper 1

Step 1

6.1.1 Steel that is used as reinforcement in concrete is available in the following thicknesses:

96%

114 rated

Answer

The correct answer is: A 8 mm, 25 mm and 40 mm. This standard thickness is widely used in various concrete reinforcement applications.

Step 2

6.1.2 Reinforcement rods and bars are available in lengths of up to …

99%

104 rated

Answer

The correct answer is: C 12 000 mm. This length is sufficient for most construction purposes.

Step 3

6.1.3 Bars are used to prevent the reinforcement from …

96%

101 rated

Answer

The correct answer is: D All the above-mentioned. Reinforcement bars are crucial for maintaining dimension stability under various forces.

Step 4

6.1.5 The purpose of minimum concrete cover is to ensure …

98%

120 rated

Answer

The correct answer is: D All the above-mentioned. Minimum concrete cover is essential for ensuring durability and safety.

Step 5

6.2 Give TWO reasons for the installation of pile foundations.

97%

117 rated

Answer

  1. Poor soil conditions: Pile foundations help stabilize structures where the surface soil is weak or unstable, such as soft or loose soil.
  2. Load distribution: They distribute loads more evenly to deeper, more stable soil layers, reducing the risk of settling.

Step 6

6.3 Draw a neat freehand sketch in your ANSWER BOOK showing the first step of the installation of a driven in-situ pile.

97%

121 rated

Answer

The sketch should include:

  • Steel cable: Depict it correctly at the top of the pile.
  • Steel pipe-casing: Shown as surrounding the pile.
  • Drop hammer: Illustrate it correctly as the tool used for driving the pile.
  • Any ONE label: Clearly label the components to show understanding.

Step 7

6.4.1 Predict TWO consequences of installing the rib and block floor as shown.

96%

114 rated

Answer

  1. Structural instability: The block may not support proper weight distribution, leading to potential collapse or fall-through.
  2. Risk of excessive weight: Without sufficient openings, the block can accumulate undue stress from lack of ventilation and moisture.

Step 8

6.4.2 Draw a neat freehand drawing in your ANSWER BOOK and rectify the faults in FIGURE 6.4.

99%

104 rated

Answer

The drawing should fix highlighted errors:

  • Ensure proper reinforcement in the ribs.
  • Illustrate correct rebates or supports to strengthen the structure.

Step 9

6.4.3 What is the minimum recommended width of the load-bearing walls that support this type of floor construction?

96%

101 rated

Answer

The minimum recommended width for load-bearing walls supporting rib and block floors is 220 mm.

Step 10

6.5 Use ANSWER SHEET 6.5 and draw a neat sectional view of a round reinforced concrete column with eight main bars in good proportion.

98%

120 rated

Answer

The sectional view should show:

  • Column: Depicted as a circular shape.
  • Main bars: Eight evenly spaced bars inside the column.
  • Stirrups: Included as necessary reinforcement.
  • Cover depth: Clearly indicated with appropriate measurements.

Step 11

6.6.1 The area of the floor

97%

117 rated

Answer

To calculate the area: Using the dimensions:

  • Length: 6 500 mm
  • Width: 4 500 mm

The area is calculated as: extArea=extLengthimesextWidth=6500imes4500=29,250,000extmm2=29.25extm2 ext{Area} = ext{Length} imes ext{Width} = 6 500 imes 4 500 = 29,250,000 ext{ mm}^2 = 29.25 ext{ m}^2

Step 12

6.6.2 The volume of concrete needed for the floor. Round off your answer to TWO decimal places.

97%

121 rated

Answer

To calculate the volume of concrete: Using the area calculated and the thickness:

  • Area: 29.25extm229.25 ext{ m}^2
  • Thickness: 0.075extm0.075 ext{ m}

The volume is: extVolume=extAreaimesextThickness=29.25imes0.075=2.194extm3 ext{Volume} = ext{Area} imes ext{Thickness} = 29.25 imes 0.075 = 2.194 ext{ m}^3 Rounding off to two decimal places: 2.19 m³.

Step 13

6.6.3 The number of tiles needed.

96%

114 rated

Answer

To find the number of tiles:

  • Size of one tile: 350extmmimes350extmm=0.1225extm2350 ext{ mm} imes 350 ext{ mm} = 0.1225 ext{ m}^2
  • Total area to be covered: 29.25extm229.25 ext{ m}^2

The number of tiles is calculated as: ext{Number of tiles} = rac{ ext{Total area}}{ ext{Area of one tile}} = rac{29.25}{0.1225} = 239.22 ext{ tiles} Rounding up gives 240 tiles needed.

Join the NSC students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;