3.1 Give ONE word/term for each of the following descriptions by choosing a word/term from the list below - NSC Civil Technology Woodworking - Question 3 - 2022 - Paper 1
Question 3
3.1 Give ONE word/term for each of the following descriptions by choosing a word/term from the list below. Write only the word/term next to the question numbers (3.1... show full transcript
Worked Solution & Example Answer:3.1 Give ONE word/term for each of the following descriptions by choosing a word/term from the list below - NSC Civil Technology Woodworking - Question 3 - 2022 - Paper 1
Step 1
3.1.1 The horizontal member between the casement frame, fixed to the wall by means of horns on both ends
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Sill
Step 2
3.1.2 The middle vertical member between the casement stiles
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Mullion
Step 3
3.1.3 The outer vertical member of the frame
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Frame stile
Step 4
3.1.4 The horizontal member that separates the casement and the fanlight
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Transom
Step 5
3.1.5 The horizontal members between the rails of a casement.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Glazing bars
Step 6
3.2 Draw, in your ANSWER BOOK, a neat freehand sketch of the sectional view of only the top rail of a casement.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The sketch should depict the top rail, showing details like the rebate and hatching to indicate material sections.
Step 7
3.3.1 Identify parts A to C.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
A - Front rail/Top rail
B - Intermediate side
C - Kick plate/Base plate/Base/Plinth
Step 8
3.3.2 Describe the purpose of a hanging rail in a cupboard.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To hang clothes on.
Step 9
3.3.3 Draw, in your ANSWER BOOK, a neat freehand sketch of section D–D.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The sketch should display the vertical section of the cupboard, including back, sides, and hatching.
Step 10
3.4 Use ANSWER SHEET 3.4 and draw in good proportion, a vertical sectional view of the wall panel.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The drawing should accurately represent the wall panel with hatching to indicate the material.
Step 11
3.5.1 The total length of the rafters needed if the length of the rafter is 5 600 mm.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Total length = 8 imes 5.6 ext{ m} = 44.8 ext{ m}
Step 12
3.5.2 The total length of the purlins needed if the length of the purlin is 9 600 mm.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Total length = 4 imes 9.6 ext{ m} = 38.4 ext{ m}
Step 13
3.5.3 The total area of underlay needed if the underlay ends on the outside walls.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Total area = 1/2 imes 9.0 ext{ m} imes 5.0 ext{ m} = 45.0 ext{ m}^2