Read the scenario below and answer the question that follows - NSC Consumer Studies - Question 5 - 2018 - Paper 1

Question icon

Question 5

Read-the-scenario-below-and-answer-the-question-that-follows-NSC Consumer Studies-Question 5-2018-Paper 1.png

Read the scenario below and answer the question that follows. After renting a house for many years José decided to build a house. He hired an unskilled builder from... show full transcript

Worked Solution & Example Answer:Read the scenario below and answer the question that follows - NSC Consumer Studies - Question 5 - 2018 - Paper 1

Step 1

Analyse the disadvantages for José having a house built.

96%

114 rated

Answer

  1. The building house was more expensive as José spent more money than was anticipated due to unforeseen complications related to the builder’s lack of skill.

  2. Building became complicated for José, as the builder was unskilled and inexperienced, which caused delays and extra costs. This was due to the builder being unfamiliar with building standards and regulations.

  3. The building quality was poor, highlighted by poor workmanship, which contributed to issues with skew walls. This poor execution required the walls to be rebuilt multiple times.

  4. José had to pay rates and taxes, such as property rates and water/sewage disposal, for the land even though he didn’t occupy the house yet.