Andrew and Duncan went fishing for carp on a friend's farm - NSC Mathematical Literacy - Question 3 - 2023 - Paper 2
Question 3
Andrew and Duncan went fishing for carp on a friend's farm.
NOTE: Carp is a large freshwater fish that can be eaten by humans.
3.1.1 A female carp can lay 2,7 mill... show full transcript
Worked Solution & Example Answer:Andrew and Duncan went fishing for carp on a friend's farm - NSC Mathematical Literacy - Question 3 - 2023 - Paper 2
Step 1
3.1.1 Write 2,7 million in full, using numerals only.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
2,700,000
Step 2
3.1.2 Determine, in kg, the total mass of the carp they caught.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The total mass of the carp is calculated as follows:
Mass of Andrew's carp: 2,375 kg
Mass of Duncan's carp:
First carp: 1.2 kg
Second carp: 0.750 kg or 0.75 kg
Total mass = 2.375 kg + 1.2 kg + 0.75 kg = 4.325 kg
Thus, the total mass of the carp they caught is 4.325 kg.
Step 3
3.2.1 Calculate, in m³, the total capacity of all the holes dug for the required posts.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The volume of one hole is calculated using the formula:
Volume = length × width × depth
= 0.3 m × 0.3 m × 0.6 m = 0.054 m³
For 12 holes:
Total volume = 12 × 0.054 m³ = 0.648 m³
Step 4
3.2.2 Give an explanation why he had some concrete left over after planting all the posts in the holes with concrete.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The reason Andrew had some concrete left over could be due to the fact that when mixing concrete, there is always some excess material that does not get used completely when pouring into the holes. Additionally, some volume may have been lost in spillage or during the mixing process. Therefore, even though he calculated the exact volume required, practical losses in concrete mixing and pouring would result in some leftover concrete.
Step 5
3.2.3 Calculate the mass of river sand needed to make 1 m³ of concrete.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To determine the mass of river sand needed for 1 m³ of concrete:
The ratio of cement to river sand to stone is given. Since we're told 0.75 m³ of concrete requires 5.5 bags of cement, we need to find the equivalent mass of river sand for 1 m³.
Mass of river sand needed for 1 m³ can be calculated:
Since 0.75 m³ uses 5.5 bags of cement, 1 m³ uses (5.5 / 0.75) × 1 = 7.33 bags of cement.
Each bag of cement weighs 50 kg, therefore:
Mass of cement = 7.33 bags × 50 kg/bag = 366.5 kg.
The remaining portion (river sand and stone) needs to be calculated based on proportions according to the initial statement.
Step 6
3.3.1 Calculate, in cm², the total area of all the post sides that have to be painted.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Each concrete post has two sides to paint:
Area = 2 × (length × width)
= 2 × (1.6 m × 0.125 m) = 0.4 m² or 4,000 cm²
For 12 posts:
Total area for posts = 12 × 4,000 cm² = 48,000 cm².
Step 7
3.3.2 Verify, showing all calculations, whether Duncan's statement is VALID.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To verify Duncan's statement:
Calculate the total area of the posts combined and the caps.
The total area of the posts and caps is calculated by adding Their areas:
Use the earlier calculated area of the posts and post caps respectively.
Total should match or differ from 52,704 cm² to validate.
Step 8
3.3.3 Calculate how many litres of paint is needed to paint 52 704 cm².
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To calculate the litres of paint needed:
Given spread rate = 12.46 litre/m²,
Total area = 52,704 cm² is equivalent to 5.2704 m².
Litres of paint needed:
= Total area / spread rate
= 5.2704 m² × 12.46 litre/m² = 65.70 litres.